Judge rejects environmental report for Tejon Ranch’s Grapevine project

Tejon Ranch executive Greg Bielli and a grapevine development

Environmentalists won another reprieve in their long-running effort to derail a sprawling new housing development north of Los Angeles County.

Late last week, Kern County Superior Court Judge Kenneth Twisselman rejected the project’s environmental impact report and ruled that Kern County must rescind its approvals for the 8,000-acre Grapevine Development proposed by Tejon Ranch.

The judge said the county and Tejon Ranch needed to provide further analysis about the traffic impacts of the master-planned community. Once that is complete, the Kern County Board of Supervisors will need to recertify the project’s Environmental Impact Report.

The ruling comes five months after the court said the county failed to analyze the full environmental impact of the project.

Kern County’s Board of Supervisors unanimously approved the mixed-use development in 2016. Tejon Ranch, the small publicly traded developer behind the project, and several others, received entitlements for 12,000 residential units, and about 5.1 million square feet of commercial development.

About a month later, the Center for Biological Diversity and Center for Food Safety brought their complaint against the project in Kern County Superior Court, citing issues with the environmental report.

The court decided in July that Kern County was in violation for failing to analyze the full scope of the air quality and public health concerns related to the project. At the time, it did not determine whether the county had to revoke project approvals.

On Dec. 7, Judge Twisselman ruled against the environmental groups on six other issues.

A spokesperson for Tejon Ranch said the firm “looks forward to satisfying the judge’s order and moving the plan forward.”

Last week’s ruling comes just days before the L.A. County Board of Supervisors gathers to review another one of Tejon’s master-planned communities, Centennial. On Tuesday, the board will meet to review the highly contentious project, which has been in the pipeline for more than two decades.

If approved, the project would bring nearly 20,000 units of housing and 10 million square feet of commercial space to an undeveloped area about 60 miles north of L.A city.

Powered by WPeMatico

  • 10 December 2018
  • The Real Deal
  • Uncategorized
  •  Like
Kidder Mathews opens new office with 21 former Charles Dunn recruits →← Travis Kalanick’s real estate venture picks up downtown San Jose building
  • Recent Posts

    • Westchester resi project gets city OK after union drops objection May 23, 2025
    • WATCH: ‘Father of CMBS’ Ethan Penner to run for governor of California May 23, 2025
    • Fashion Island office fetches $756 psf May 23, 2025
    • Resi occupancy soars above pre-pandemic levels in Downtown LA May 22, 2025
    • Hines gets key approval on Arts District office project May 22, 2025
  • Recent Comments

    • Archives

      • May 2025
      • April 2025
      • March 2025
      • February 2025
      • January 2025
      • December 2024
      • November 2024
      • October 2024
      • September 2024
      • August 2024
      • July 2024
      • June 2024
      • May 2024
      • April 2024
      • March 2024
      • February 2024
      • January 2024
      • December 2023
      • February 2023
      • January 2023
      • December 2022
      • November 2022
      • October 2022
      • September 2022
      • August 2022
      • July 2022
      • June 2022
      • May 2022
      • April 2022
      • March 2022
      • February 2022
      • January 2022
      • December 2021
      • November 2021
      • October 2021
      • September 2021
      • August 2021
      • July 2021
      • June 2021
      • May 2021
      • April 2021
      • March 2021
      • February 2021
      • January 2021
      • December 2020
      • November 2020
      • October 2020
      • September 2020
      • August 2020
      • July 2020
      • June 2020
      • May 2020
      • April 2020
      • March 2020
      • February 2020
      • January 2020
      • December 2019
      • November 2019
      • October 2019
      • September 2019
      • August 2019
      • July 2019
      • June 2019
      • May 2019
      • April 2019
      • March 2019
      • February 2019
      • January 2019
      • December 2018
      • November 2018
      • October 2018
      • September 2018
      • August 2018
      • July 2018
      • June 2018
      • May 2018
      • April 2018
      • March 2018
      • February 2018
      • January 2018
      • December 2017
    • Global Property and Asset Mangement, Inc.
      137 North Larchmont
      Los Angeles, California 90010
      +1 213-427-1127

    © 2025 GPAM